Managing the Risks Presented by Pipeburst, Redundant and Live Asbestos Cement Pipe Water Distribution Mains: Estimation of the Costs Associated with Different Rehabilitation Techniques
Price: £50
Ref: 04/WM/03/19
ISBN: 1-84057-382-1
The objective of this study was to estimate the relative costs of each rehabilitation option in order that all acceptable options (with respect to risk) can be compared financially.
Standard Ofwat costs (benchmark and mid point) were used to determine the relative costs of five rehabilitation techniques. These costs were for all materials, consequently, additional costs specific to asbestos cement pipes were identified and listed.
The costs given are the lowest value due to the nature of the Ofwat costs, and are likely to underestimate the true costs. Conclusions and recommendations are also made.
Customers who bought this report also bought...
The Environmental Impact of Phosphorus from the Agricultural Disposal of Sewage Sludge - Stage 3
97/SL/02/4 - ISBN: 1 84057 013 XLaboratory, lysimeter and field studies continue to show wide variability the potential bioavailability of phosphorus in sewage sludge. Under operational rates of application, losses of phosphorus in run-off from plots recei... More...
Price: £100
A Survey of Practices for the Detection and Location of Leaks
11/WM/08/45 - ISBN: 1 84057 592 1The objective of this report is to provide guidance in the application of leak localising and detection techniques to individuals responsible for managing the leak detection process. Implementing the recommendations sh... More...
Price: £250
Managing the Risks Presented by Pipeburst, Redundant and Live Asbestos Cement Pipe Water Distribution Mains: Project Summary Report
04/WM/03/16 - ISBN: 1-84057-379-1The objective of this report was to summarise the work carried out in the complete project and update the water industry on legislation. This report provides a useful introduction to the 3 more detailed reports from this p... More...
Price: £50
Managing the Risks Presented by Pipeburst, Redundant and Live Asbestos Cement Pipe Water Distribution Mains: Risk Assessment of Asbestos Fibre Release During Rehabilitation of Asbestos Cement Water Mains
04/WM/03/17 - ISBN: 1-84057-380-5The objective of this study was to derive quantitative values for asbestos fibre concentrations released by a range of rehabilitation options and a range of conditions. These data would be incorporated into the qualitative... More...
Price: £150
Managing the Risks Presented by Pipeburst, Redundant and Live Asbestos Cement Pipe Water Distribution Mains: Condition Assessment Methodology for Asbestos Cement Pipes
04/WM/03/18 - ISBN: 1-84057-381-3The objective of this study was to develop a methodology for predicting the condition of AC water pipes and identify how GIS could be used to report this information. Each of the factors affecting condition of pipe... More...
Price: £100
©